September 2005 – January 2006

Ashurst – Stillorgan. Demolish existing concrete framed buildings 4 no in total. Grub up concrete slabs and foundations and cart away. Excavate bulk dig to basement 4m deep and cart away. Carry out sheet piling to perimeter of site for ground stabilisation with rakers and whalers. Excavate site services (ESB Gas, fibre optic cables) outside perimeter of site. Form hardstandings for piling ring etc.

 

July 2005 – October 2007

Kilmainham/ Cork Street. Demolish existing concrete framed buildings 4 no in total. Grub up concrete slabs and foundations and cart away. Excavate bulk dig to basement 4m deep and cart away. Carry out sheet piling to perimeter of site for ground stabilisation with rakers and whalers. Excavate site services (ESB Gas, fibre optic cables) outside perimeter of site. Form hardstandings for piling ring etc.

 

June 2005 – September 2005

INS Trinity. Demolish concrete framed building with concrete flat roof containing asphalt. Grub up concrete floor slab and foundations and cart away.

 

May 2005 – August 2005

Camden Street. Demolish existing old Georgian Building consisting of brickwork and stonework and grub up concrete floor slab and foundation and cart away. Excavate bulk dig to basement (all soil contaminated) and cart away to licenced tips. Carry out underpinning to surrounding buildings.

 

April 2005 – March 2007

Shelbourne Hotel, Dublin. This work is being carried out to the rear of the main building, which is being restored. The buildings being demolished are contained within the ‘courtyard’ formed by the main building. The department of Agriculture is immediately adjacent to the demolition project.

Demolish parts of existing structures and demolish parts of RC walls, block walls, and plasterboard partitions internally and cart away. Carrying out builders works, forming opes, needle and pinning and inserting structural steelwork to support existing walls. Carry out all drainage works (by hand) in basement area and excavate and lay site service and complete external works package around hotel service yard.

 

April 2005

37 - 38 Capel Street 3 Storey Building. Protected/listed building; front façade retained and propped by temporary steelwork. Demolition works package contained - removing roof complete, remove all timber floors. Excavate bulk dig to form new basement. Carry out to stage underpinning.

 

April 2005

29 Woodlands Park for E H Construction. The front façade of the house was retained with all of the remainder being demolished. Both adjoining properties were occupied during the works.

 

April 2005

Demolition of 19 Sandymount Avenue for John G Burns. This building is the former Teagasc building and is adjacent to the taxation institute and occupied dwelling houses. The demolition will be carried out sensitively and will respect the adjoining occupiers.

 

February 2005 – March 2005

Wellington Lane and Blessington Street - AP Tobin Limited. This demolition took place around the still trading iron workshops facing onto the main road.

 

February 2005 – May 2005

Demolition works at the Kilternan Sports Hotel for Bowen Construction. This project included the complete demolition of some of the buildings and the gutting out of others. With the exception of Springfield House, a protected structure, all of the retained buildings were returned to their structural state.